Convection parts (boiler tubes) for Unit 1 and 4 in the Uppsala Waste incineration plant

Vattenfall AB Procurement Heat Sweden, Solna

Sista anbudsdag
24 nov 2025
Uppskattat värde
90 mkr
Avtalstid
Ej angiven
Förfarande
Förhandlat med annonsering
Plats
Uppsala län
Bransch
Bygg och anläggning45351000

Konkurrens

Normal ≈ 4,9 anbud

2 088 liknande tilldelningar inom bygg och anläggning de senaste tre åren.

Har vunnit hos köparen förut

Typiskt värde

79,8 mkr

Median per avtal i kategorin. Köparens tidigare: 41 mkr.

  1. Publicerad11 nov 2025
  2. Sista anbudsdag24 nov 2025
  3. I dag4 nov 2026

Konkurrensbild

Bygg och anläggning, hela Sverige, senaste tre åren

Normal konkurrens. Räkna med 4–6 anbud.

Underlag: 2 088 tilldelningar som anger antal anbud. Beräknat av Anbudsläget från TED.

Antal anbud per tilldelning
Anbud i snitt
4,9
Fick bara ett anbud
11 %
Medianvärde per avtal
79,8 mkr
Vanns av små och medelstora
60 %

Köparens tidigare avtal i samma område

1 senaste

Troliga konkurrenter

Flest vinster inom bygg och anläggning
Pro

Vilka ni troligen möter

De 8 leverantörer som vunnit flest avtal inom bygg och anläggning de senaste tre åren, med antal vinster och värde.

Prova Pro gratis14 dagar, inget kort
Konkurrensen i just Uppsala län, jämfört med hela landetProva Pro gratis

Beskrivning

LTE Investment for Unit 1 and 4 in the Waste incineration Plant AFA in Uppsala, Sweden. ​ The waste incineration plant in Uppsala consists of a total of three waste boilers, two of which are from the 80s and one that was commissioned in 2005. The waste incinerators are the base production units of district heating and steam in Uppsala. On the two older waste boilers, Unit 1 and 4, it is time to replace pressure vessel parts (convection parts) in order to continue operations until 2040. Other parts (membrane walls in furnace and the so-called “lattice tubes” have previously been replaced and supplemented with overlay welding. The steam data is 15 bar(g) and 200°C for both boiler. This procurement concerns replacement of the convection parts in the horizontal pass (three evaporator bundles and one economizer) of Unit 4, to be carried out during summer overhaul of 2026. As an option we also ask for replacement of the corresponding parts of Unit 1 during the summer of 2027. As another option, the tenderer shall also include replacement of the membrane walls surrounding the horizontal passes. The Purchaser will supply detailed drawings of the existing tube bundles and the Contractor shall design, manufacture and install the new tubes with necessary adaptations to modern criteria for design, testing and inspection. Also included in the scope is a new soot cleaning system for the convection parts. The tenderer shall include removal and scrapping of the old rapping system and replacement with a more modern system. The basis for the design will be a visit to the site as well as boiler drawings.
Visa hela beskrivningen